Hale, Steven J. (2019) Shutter repairs and updated fibre conversion at Carnarvon in 2019 February. Technical Report. Birmingham Solar Oscillations Network.
|
PDF
bison393.pdf 1MB |
Abstract
Carnarvon was offline due to a shutter motor failure, and a computer failure. The shutter motor and reduction gearbox was replaced with the spare from the on-site shipping container. A new computer was installed. Further work was completed on the Jabba fibre conversion to resolve some ongoing issues and return the instrument performance and data quality to expected levels.
| Type of Work: | Monograph (Technical Report) |
|---|---|
| School/Faculty: | Colleges (2008 onwards) > College of Engineering & Physical Sciences |
| Number of Pages: | 11 |
| Department: | High-Resolution Optical Spectroscopy |
| Date: | 27 March 2019 |
| Projects: | BiSON - Birmingham Solar Oscillations Network |
| Series/Collection Name: | BiSON Technical Report Series |
| Keywords: | Helioseismology, Observations; Oscillations, Solar |
| Subjects: | Q Science > QB Astronomy Q Science > QC Physics |
| Related URLs: | |
| ID Code: | 3210 |
|